Coolidge to Valley Farms 115kV Rebuild Project
Spartan successfully completed the project six weeks ahead of schedule and received an exceptional performance review.
Procure and Construct (PC) 115kv Rebuild Project Permitted Under the National Environmental Policy Act (NEPA).
Scope of Work
- Replacement of wood H-frame structures
- Removal of 4/0 Copper conductor and 3/8-inch-high strength (HS) steel overhead ground wire (OGW)
- Installation of 954-KCMIL ACSR, Cardinal conductor, 48 fiber OPGW, 3/8” HS OGW
- Installation, termination, and testing of fiber optic cable in the Coolidge and Valley Farms substations
More Projects
Taygete Solar 138kV Transmission Line Project
Spartan’s acceleration plan enabled a high rate of safe production that allowed our customer to meet its required interconnection date
Solstice to Bakersfield 345kV
Spartan mobilized critical personnel and equipment to complete wire installation within a compressed
project schedule