Coolidge to Valley Farms 115kV Rebuild Project
Spartan successfully completed the project six weeks ahead of schedule and received an exceptional performance review.
![](https://spartaninfra.com/wp-content/uploads/2021/03/Coolidge-PAGE-BANNER.jpg)
Procure and Construct (PC) 115kv Rebuild Project Permitted Under the National Environmental Policy Act (NEPA).
Scope of Work
- Replacement of wood H-frame structures
- Removal of 4/0 Copper conductor and 3/8-inch-high strength (HS) steel overhead ground wire (OGW)
- Installation of 954-KCMIL ACSR, Cardinal conductor, 48 fiber OPGW, 3/8” HS OGW
- Installation, termination, and testing of fiber optic cable in the Coolidge and Valley Farms substations
![](https://spartaninfra.com/wp-content/uploads/2021/03/Coolidge-SCOPE.jpg)
More Projects
Taygete Solar 138kV Transmission Line Project
Spartan’s acceleration plan enabled a high rate of safe production that allowed our customer to meet its required interconnection date
Solstice to Bakersfield 345kV
Spartan mobilized critical personnel and equipment to complete wire installation within a compressed
project schedule