Taygete Solar 138kV Transmission Line Project
Spartan’s acceleration plan enabled a high rate of safe production that allowed our customer to meet its required interconnection date
Construction of a 138kv Double Circuit Transmission Line Project Located near Pecos, Texas.
Scope of Work
- Installation of (27) caisson foundations and (71) direct embed steel monopoles
- Installation of 10 miles of double circuit and 1 mile of single circuit two bundle 954-KCMIL ACSR conductor and two bundle 48 count OPGW
- ROW services include installation and repair of fences and gates
- Installation, maintenance, and removal of Stormwater Pollution Prevention BMPs
More Projects
Coolidge to Valley Farms 115kV Rebuild Project
Awarded the procure and construct project in 2019, Spartan successfully completed the project six weeks ahead of schedule, and received an exceptional performance review.
Solstice to Bakersfield 345kV
Spartan mobilized critical personnel and equipment to complete wire installation within a compressed
project schedule