Coolidge to Valley Farms 115kV Rebuild Project
Awarded the procure and construct project in 2019, Spartan successfully completed the project six weeks ahead of schedule, and received an exceptional performance review.
Awarded the procure and construct project in 2019, Spartan successfully completed the project six weeks ahead of schedule, and received an exceptional performance review.
Spartan’s acceleration plan enabled a high rate of safe production that allowed our customer to meet its required interconnection date
Spartan mobilized critical personnel and equipment to complete wire installation within a compressed
project schedule
Despite significant schedule delays due to excessive rainfall, Spartan completed this 9-mile, single circuit, 138kV transmission line project by the original substantial completion date, with zero accidents, injuries, or lost time incidents.
Spartan rapidly mobilized equipment and personnel to accelerate conductor, OPGW, anchor, and guy wire installation for a section of this 18-mile 345kV transmission line project. Spartan successfully completed construction of the transmission line with zero accidents, injuries, or lost time incidents.
Spartan mitigated an adverse schedule impact caused by significant rainfall events by modifying the construction plan to include utilization of timber matting to facilitate safe access to structure sites while also using specialized track mounted equipment to minimize unnecessary property damage. Spartan completed the project two weeks ahead of schedule and successfully restored the ROW to the satisfaction of our customer and private landowners
The Port 138kV Transmission Line Connection project was a single circuit 138kV transmission line construction project located near Victoria, Texas. Construction activities performed by Spartan included the installation of direct embed foundations and concrete poles. The structures installed included anchors and guys at each deadend location. Wire stringing activities included the installation of 795 kcmil “Drake” conductor.
Construction activities performed by Spartan included installation of drilled pier and direct embed foundations as well as installation of tangent and deadend structures. Wire installation consisted of two-bundle 795 kcmil 26/7 ACSR “Drake” and two (2) 48-count OPGW. Access road construction and restoration was also included within Spartan’s work scope. Spartan met all critical Project milestones on this 5 mile, 345kV transmission line near Kenedy, TX.
Spartan was specifically selected to perform the construction on the Latimer 345kV Transmission Replacement Project due to the complexity and coordination required to remove existing 345kV transmission facilities in a constrained work area adjacent to a major 345kV substation. The work was performed under an outage window that provided limited time for all work to be performed. A detailed work plan was developed through significant on‐site preconstruction coordination with the project owner and engineer.
Spartan’s scope for this 345kV transmission line project consisted of the installation of conductor and OPGW deadend assembles, installation of OPGW splice assemblies and downlead clamps, sagging, clipping, and dead-ending of two-bundle 795 ACSR “Drake” as well as one (1) 48-count OPGW and one (1) 3/8” 7-Strand EHS static wire on existing lattice structures. Spartan completed this 345kV transmission line project on schedule with an exceptional safety record.